HARCO successfully exchanged 4 gearboxes at Horns Rev 1 in June 2021.
Despite challenges due to bad weather, all gearboxes were exchanged within the 13 days window, including all preparatory and finalizing works.

HARCO strives to keep the turbines running, increasing availability while simultaneously reducing jack-up charter rates.

This was achieved in close collaboration with the Vattenfall Main Component Exchange team, site crew and Jack-up supplier, enabling an optimum execution.

HARCO supported Vattenfall in exchanging 4 gearboxes in record time at Horns Rev 1. In cooperation with HARCO, we are now able to perform main component exchanges with a minimum of jackup charter rates.”

Karl Jørgensen

Main Component Supervisor, Vattenfall

About the Wind Farm
The Wind Farm is located 20 kilometers off the western coast of Jutland in Denmark. The wind farm was upon installation, the world’s largest offshore wind farm, consisting of 80 turbines, generating power for approx. 150,000 private households. The wind farm occupies 20 square kilometers and was installed in 2002.

The wind conditions in this area are ideal for wind power generation, but can also result in difficulties during CTV transit, or when exchanging components on the turbines. (source: powerplants.vattenfall.com)

About HARCO
HARCO’s goal is to revolutionize the lifting industry with better and smarter applications, prepared for the future. The criteria of success are to provide advisory and knowhow to develop sustainable, cost efficient and cutting-edge solutions for the industry.

HARCO offers wind farm all-in services, main component exchanges, specialist services, equipment specialist services, and development and maintenance of equipment.

HARCO is a great supplier for us, as they are focused on value-adding services. This means that we can cost optimize by utilizing existing site equipment and staff, and leave the remaining scope with HARCO.”